January 2025 Build Diary

Week 1

As we embark on a new year, we reignite our passion for driving existing projects forward, fostering innovation, and paving the way for a brighter, more prosperous future filled with growth, improvement, and boundless possibilities. 

To do list for week 1:-

·         Aluminium Sub frame

·         Custom Swing-arm production

·         Quick Throttle Design

·         SR 16 Chassis 3 welding

·         SR 16 Chassis 4 tube bending

 

We had our own design for our SR 16 Sub Frame. Its main purpose is to improve the agility of the bike and decrease rear weight of the bike. We started producing the aluminum sub frame, One of the major challenges for this is the welding. This aluminum subframe is of the same design as the steel one. We have just done it for the weight reduction and agility purpose.  

 

We had the design of the aluminum quick throttle from the design team by mid week. We started manufacturing the base of the quick throttle in Lathe Machine and it came out to have a very good finish. Our aluminum quick throttle are designed and developed for racing performance. It is developed after doing intense testing on track by our riders. 

 

 

Week 2

To Do list :-

·         SR16 Battery box design and assembly.

·         Installing the liquid cool system in SR16.

·         SR 16 Chassis 4 welding and assembly.

Battery Box design was ready. The design is mainly based keeping in mind to accommodate the liquid cooled system, new motor, controller. Its was a new design for the battery box. The parts of the battery box was produced with aluminum sheet for weight reduction purpose. This design is one of the unique designs we have produced which improved the center of gravity of the bike also. 

 

We have currently 2 same chassis under development Proloy 1 & 2. We have installed the liquid cooled system in one of them to compare the performance of both the motor under different circumstances.

 

Week 3

To do list :-

  1. Call assembly according to the battery box.
  2. Assembly of Proloy 2 & testing it on track
  3. Quick throttle tube cutting and welding.
  4. Custom Aluminum Swingarm production.